Canalino/Family School

The conceptual plan for Canalino / CFS provides a unique identity for both schools and provides the appropriate separation between “little kid” and “big kid” areas. Restrooms campus-wide will be modernized. Other improvements include upgrading existing classrooms, remodeling the kitchen, upgrading finishes in the MPR and addressing the special education patio area. After school programs will now have a permanent home. New construction on site includes a new learning center and classrooms.

Site allocation

$19,096,015

Completed Projects

Campus Modernization Phase 3

The modernization of Buildings A and H (Phase 3) included: remodeling and updating restrooms to current ADA accessibility standards; updating mechanical, communications and fire alarm systems; updating lighting and door hardware and replacing certain exterior and interior finishes.

With the completion of three phases of modernization, the six interim housing portables were also removed this summer. Three additional portables at the east end of the campus will be removed in December 2020. Following those removals, the only portable buildings remaining on campus are the library and the computer lab.

Campus Modernization Phase 1

All of the classrooms in Buildings C and D at Canalino/Carpinteria Family School were modernized, outfitted with new furniture and the latest Teacher Tech Tools during Summer 2019, and were ready for students at the start of the 2019-2020 school year.

Phase 2

The modernization of Building G began in October 2019 and wrapped up in January 2020. The construction cost for Phases 1 and 2 totaled $4.8 million.

Campus Modernization Phase 2

The modernization of Building G began in October 2019 and wrapped up in January 2020. The construction cost for Phases 1 and 2 totaled $4.8 million.

New Modular Classrooms

The modernization of Buildings A and H (Phase 3) included: remodeling and updating restrooms to current ADA accessibility standards; updating mechanical, communications and fire alarm systems; updating lighting and door hardware and replacing certain exterior and interior finishes.

With the completion of three phases of modernization, the six interim housing portables were also removed this summer. Three additional portables at the east end of the campus will be removed in December 2020. Following those removals, the only portable buildings remaining on campus are the library and the computer lab.

Multipurpose Room Interior Upgrades

The project included painting the interior of the multipurpose room (cafeteria area) and its entrance vestibule and installing new flooring and new wall-pocket folding lunch tables and benches.

Current Projects

Future phases of modernization

There are two future phases of modernization that will occur in Buildings B, E, F and J including remodeling the food service areas. The Learning Resource Center (LRC) is also anticipated in a future phase. The construction of these two phases of modernization as well as the construction of the LRC have been deferred until after the receipt of the State matching funds anticipated in fiscal year 2022-2023.