Carpinteria Middle School
The Carpinteria Middle School conceptual plan calls for all portables on site to be replaced with new modulars. To accommodate the new classroom layout, the track needs to be reconfigured and will become a 400-meter track.
The main building and multipurpose room will also be improved with renovations to classrooms, the old locker rooms, music and band rooms. New shade structures will be provided throughout the campus for student comfort. The entrance will also be redesigned to provide a secure single point of entry to the campus.
Site Allocation
$10,208,510
Measure U funds: $9,934,400
State funds: $274,110
Completed Projects
New Modular Classrooms & Track Reconfiguration
Completed January 2019
Construction Cost: $4,213,506
The construction of (8) Gen7 modular classrooms and an adjoining restroom was completed in January 2019. Each classroom was outfitted with new furniture and the latest Teacher Tech Tools. The interim housing was removed plus three portable classrooms eradicating all portable classrooms from the site. CMS is the first campus to be rid of all portable classrooms! Providing healthy, high quality, energy efficient learning spaces is the primary goal of Measure U. The track at CMS was also upgraded and reconfigured earlier this year.
Remodel Staff and Student Restrooms
Completed August 2018
Construction Cost: $220,000
One set of staff and student restrooms in the main building at CMS was updated to comply with current accessibility standards.
Improved Security at Front Entry
Completed August 2018
The front entry is now secured during school hours. Visitors are viewed by a security camera and must “buzz” the front office prior to gaining entry.
Art & Shop Building Roof Replacement
Completed August 2017
Construction Cost: $181,423
Multipurpose Building Roof Replacement
Completed August 2016
Construction Cost: $176,087